Kaufmann Center Renovations and Addition

 

 

SCORE: 91%

DISPOSITIONProject aligns with the Greater Hill District Master Plan

 

View the Executive Summary

View the Project Narrative

MWBE Strategy

View the Project Team Info

View the Architectural Renderings and Floor Plan

View the Letter of Support

 

November 2019 - Submitted to the DRP

  • 25'x82' one story addition with basement to an existing three story structure.
  • Approximately 4000 sf of existing
    space on the second and third floors (2000 sf/floor) will be renovated.
  • The existing use is as a Community Center
    and will continue that use under new ownership, providing after-school and summer camp art programming to local
    youth.
  • This building will also be available for continued community events and rental space.
  • Seeking zoning approvals

 

December 2019 - DRP conducted an internal review of the proposal

  • The DRP met and reviewed the proposal during their monthly meeting
  • The DRP agreed to formally invite the developer to present in January and provided feedback in preparation for that presentation

 

January 2020 - Presented to the DRP

  • The DRP scored the proposal a 87% and thus determined the project was in alignment with the Greater Hill District Master Plan
  • The development team has been invited to present at the next community meeting in February 2020

 

 

February 2020 - Community Meeting Presentation

  • The development team presented at the community meeting February 20, 2020
  • The project receieved a 97% from the community.
  • The project scored a cumulative 91% and is therefore in alignment with the Greater Hill District Master Plan
  • The developer recieved a letter of support on February 27, 2020 

 

 